good news from Caltrans/DOT:

Mr. Comeau

Barring any unforeseen circumstances the frontage roads should be open to the public sometime in July 2014.

The bike path will be completed shortly thereafter and will be connected to the frontage roads and will be opened no later than 12/31/14.

The bike path and the frontage road cannot be opened simultaneously because of staging related issues.

The existing Olompali off-ramp needs to be closed off in order to place box culverts across the bike path.

The K-rail on the mainline was first placed on 4/23/13 and the shoulders have been closed to the public since then.

Steve Williams

Public Information Officer